---
title: "IFS Cloud Data Migration Checklist: Five Phases to Go-Live"
date: 2026-01-30
description: "IFS Cloud data migration checklist in five phases, from source audit to the weeks after go-live, with the evidence that proves each check is done."
author: "Dariusz Mysliwiec"
intro_image: "https://www.ifs-erp.com/images/articles/ifs-cloud-data-migration-checklist-2026-edition-en-575c42e6.webp"
fulltext_image: "https://www.ifs-erp.com/images/articles/ifs-cloud-data-migration-checklist-2026-edition-en-575c42e6.webp"
categories:
  - name: "Blog"
    url: "https://www.ifs-erp.com/blog.md"
tags:
  - name: "Data migration"
    url: "https://www.ifs-erp.com/tags/data-migration.md"
  - name: "migration jobs"
    url: "https://www.ifs-erp.com/tags/migration-jobs.md"
  - name: "Data Migration Manager"
    url: "https://www.ifs-erp.com/tags/data-migration-manager.md"
  - name: "IFS Cloud"
    url: "https://www.ifs-erp.com/tags/ifs-cloud.md"
  - name: "IFS Cloud ERP Implementation"
    url: "https://www.ifs-erp.com/tags/ifs-cloud-erp-implementation.md"
---

# IFS Cloud Data Migration Checklist: Five Phases to Go-Live

![IFS Cloud Data Migration Checklist: Five Phases to Go-Live](https://www.ifs-erp.com/images/articles/ifs-cloud-data-migration-checklist-2026-edition-en-575c42e6.webp)

IFS Cloud data migration checklist · Independent IFS Cloud practice

 
## An IFS Cloud data migration checklist where every check ends in evidence you can open

 This checklist runs from the source audit to the weeks after go-live in five phases. Each check names the artefact that proves it is done, so a steering group can see the state of the migration without taking anyone's word for it.

 **Key takeaways**

 
- A data migration check is done when an artefact exists: a profiling report, a signed mapping, a trial run log or a reconciliation sheet. A status of "in progress" in a meeting is not evidence.
- Duplicates, inconsistent units of measure and text that will be truncated are found in phase 2 on the source data, before any record is loaded into IFS Cloud.
- Trial loads run in the same order and with the same rules as the cutover, and each one is timed and reconciled, so the final load repeats a known process.
- Reconciliation compares counts and values with the legacy system per data object; inventory value and open balances are compared before the go-live decision, not after it.
- The legacy system becomes read-only after go-live, and a recurring data quality check keeps new records from repeating the old faults.

 An IFS Cloud data migration is ready for go-live when every check in the five phases below has its evidence, and the open items are listed with an owner and a date. The checklist is written for the project manager and the migration lead who run the work week by week. The risks it guards against are explained in [IFS Cloud Data Migration: Five Risks That Delay Go-Live](https://www.ifs-erp.com/en/blog/ifs-cloud-data-migration). Ownership of each data object and the rule for a failed reconciliation are the subject of [the data migration governance checklist](https://www.ifs-erp.com/en/blog/the-data-migration-governance-checklist), so this article does not repeat it.

  ## 1.What has to be settled before extraction starts?

 Extraction starts only when the list of data objects to migrate is closed and the clean criteria for each object are written down. Without that list, every trial load changes scope and no two trials can be compared.

 
| Check | Evidence that it is done |
| --- | --- |
| Data objects in scope are listed | Object list with source system, target in IFS Cloud and the layer it belongs to: master data, open balances or history |
| Clean criteria are written per object | A rule per object, for example: no supplier is migrated without a valid tax ID and a country code |
| History scope is decided | A written decision on closed transactions: archived outside IFS Cloud, or listed in the data migration plan with a reason |
| Legacy custom fields are inventoried | Each custom field in the source has a decision: mapped to a standard IFS Cloud field, kept as a configured field, or left behind |
| Freeze date for legacy changes is agreed | Date in the project plan, confirmed by the business |

 The history scope decision has the largest effect on the volume of every later trial. The reasons to keep closed history out of the live environment are set out in [Legacy ERP After IFS Cloud Go-Live: Archive and Switch-Off](https://www.ifs-erp.com/en/blog/legacy-erp-archive-after-ifs-cloud-go-live).

  ## 2.Which source data faults are found before the first load?

 Source data faults are found by profiling the extract in a staging database, because a record that IFS Cloud rejects in a trial load costs a full cycle to correct, while the same fault found in staging costs one query. Profiling runs on a complete extract, not a sample.

 
1. **Duplicate customers and suppliers.** Run a duplicate report on name and tax ID, then on address, and send each candidate pair to the owner of that data for a merge decision. A supplier that trades with more than one company in the group is migrated once if the target design shares it.
2. **Units of measure.** List every unit code in use with its count of parts. Codes such as "Each", "EA" and "Pc" that mean the same thing are mapped to one unit code in IFS Cloud, and the mapping is part of the cleansing rules.
3. **Text that will be truncated.** Compare the length of each source text field, such as part descriptions, with the length of the target field and list the records that exceed it. A shortened description that nobody reviewed becomes a search problem for every buyer.
4. **Missing or impossible planning values.** Parts with an empty or negative lead time are corrected in the source or by a written default rule, because planning dates supply from lead time.
5. **Character set.** Check that names and addresses with national characters survive the extract and the staging database unchanged before mapping starts.

 The output of this phase is a profiling report per object and a set of cleansing rules. IFS Cloud migration jobs can use a conversion list to convert data before migrating, and the [Data Migration Manager documentation](https://docs.ifs.com/techdocs/25r1/030_administration/050_data_management/080_data_migration_manager/) lists inbuilt data cleansing and validation. Those tools apply the rules they are given; the rules themselves come from this phase.

  ## 3.How are mapping and trial loads checked?

 Mapping is checked by loading it, so each version of the mapping is tied to a numbered trial load with its own run log. A mock migration uses the same rules, the same load order and production-sized data, so the result says something about the cutover.

 IFS Cloud migration jobs read data from a source that, according to the [IFS Cloud data migration documentation](https://docs.ifs.com/techdocs/24r2/030_administration/050_data_management/050_data_migration/), can be a text file or an Oracle source such as a table, view or database link. The same page describes viewing the history of executed migration jobs and restarting a job for error rows, depending on the kind of error. The Data Migration Manager organises its work in container types (Input, Output, Basic Data, Deployment). Which tool fits which object is compared in the [IFS Cloud Data Migration: FndMig & DMM Field Guide](https://www.ifs-erp.com/en/blog/ifs-data-migration-fndmig-dmm).

 
| Check | Evidence that it is done |
| --- | --- |
| Mapping is versioned and signed | Mapping document with a version number, the trial it was used in and the sign-off of the data owner |
| Parts are mapped to sites and stock locations | Mapping table that lists the target sites and stock locations of every part |
| Load order follows references | Sequence in which no record loads before the records it refers to, for example a part supplier record after both the part and the supplier |
| Each trial is timed per object | Run log with start and end time per object and its error rows, kept for every trial |
| Error rows are corrected at the source or in the rules | Error list from the last trial with a cause and a fix for each group of errors; no manual edits in the target |

 A first trial on a representative subset of each object shows mapping faults early. The trials that count for go-live readiness are full volume, because only they show whether the load fits the cutover window.

  ## 4.What has to reconcile before the go-live decision?

 Counts and values in IFS Cloud have to match the legacy system for every data object before the go-live decision, within the tolerance set in the migration rules. A trial with zero load errors can still fail reconciliation, for example when parts are mapped to the wrong unit of measure.

 
1. **Record counts per object.** Source count against loaded count, with a documented reason for every record left behind on purpose.
2. **Inventory value.** Total inventory value in the legacy system against the value after the load in IFS Cloud. A difference points to the costing values or the unit of measure mapping and is explained before the next trial.
3. **Open balances.** Open payables and receivables compared by value, and open orders by value and count, at the trial cut-off date.
4. **User test with real permissions.** Key users open migrated records with their own roles, so a record that exists but cannot be seen or used by the person who needs it is found before go-live.
5. **Dress rehearsal inside the window.** A full trial in the cutover order that finishes, including reconciliation, inside the agreed cutover window.

 The rehearsal result is one of the inputs to the go-live decision. Why the cutover has to be rehearsed under real load is explained in [Go-Live Is a Load Test](https://www.ifs-erp.com/en/blog/go-live-is-a-load-test).

  ## 5.Which checks belong to cutover and the weeks after go-live?

 The cutover repeats the last successful rehearsal step by step, and the weeks after go-live check that new data does not reintroduce the faults that phase 2 removed.

 
| Check | Evidence that it is done |
| --- | --- |
| Final load follows the rehearsed sequence | Cutover run log compared with the dress rehearsal log, deviations listed |
| Final reconciliation is signed | Reconciliation sheet at the cutover date, signed before users start work in IFS Cloud |
| Legacy system is read-only | Write access removed, with a read-only archive for lookups and a planned switch-off date |
| Recurring data quality check runs | A scheduled report on the faults found in phase 2, for example parts created without a lead time, with an owner who acts on it |
| Migration artefacts are handed over | Final mapping with its cleansing rules, plus the run logs, stored where support can find them |

 Keeping the legacy system writable after go-live lets users post into two systems, and the reconciliation signed at cutover stops being true within days.

  ## 6.Turning the checklist into a plan per data object

 A checklist becomes a plan when each data object has its own row: owner, trial dates, reconciliation result, readiness status. The [Data Migration Plan and Customer Data Readiness Checklist (IDK-15)](https://www.ifs-erp.com/en/marketplace/implementation-docs-kit/15-data-migration-plan-and-readiness-checklist) is a template built that way: it lists every data object with its source, owner, method, load order and sign-off, with a customer data readiness checklist per data group. The decisions that sit above the plan, such as scope and history depth or the choice of tooling, belong in the migration strategy.

  ## 7.Frequently asked questions

 What should an IFS Cloud data migration checklist contain? An IFS Cloud data migration checklist contains checks for five phases, from the scope and source audit to cutover and the weeks after go-live. In between come profiling and cleansing, mapping with trial loads, and reconciliation. Each check names the artefact that proves it is done, such as a profiling report, a signed mapping, a trial run log or a reconciliation sheet.

   How many trial loads does an IFS Cloud data migration need? An IFS Cloud data migration needs as many trial loads as it takes for one full-volume trial to finish inside the cutover window with a signed reconciliation. The number depends on data quality and mapping changes, so the plan sets the exit criterion rather than a fixed count, and the last trial is run as a dress rehearsal in the cutover order.

   Which IFS Cloud tools load the data? IFS Cloud documents two mechanisms on docs.ifs.com: migration jobs, which read a text file or an Oracle source such as a table, view or database link and keep a history of executed jobs, and the Data Migration Manager, which works with container types (Input, Output, Basic Data, Deployment) and includes data cleansing and validation. The cleansing rules applied by either tool are written by the project during profiling.

   What should be reconciled after an IFS Cloud trial load? After an IFS Cloud trial load, the project reconciles record counts per data object and total inventory value against the legacy system at the trial cut-off date, together with open balances such as payables, receivables or open orders. Every difference is explained and fixed at the source or in the cleansing rules before the next trial.

   What happens to the legacy system after the IFS Cloud go-live? After the IFS Cloud go-live, write access to the legacy system is removed and it serves as a read-only archive for lookups until a planned switch-off date. A writable legacy system lets users post transactions in two places, which breaks the reconciliation signed at cutover.

  ## 8.About the author

 **Dariusz Myśliwiec:** 18 years hands-on with IFS (Apps 7.5 to 10 and IFS Cloud). IFS Certified Associate Consultant. PRINCE2® 7. Independent practice based in Kraków, delivered remotely across Europe and globally. You talk to the consultant who does the work, not a sales layer.

 **Selected clients from my IFS work:** Fugro · LGC · BVI Medical · Betafence (PRÆSIDIAD) · Barlinek · NGK Ceramics · Newag · Oleofarm.

 IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.

  ## Planning the trial loads for your IFS Cloud migration?

 The Data Migration Plan and Customer Data Readiness Checklist (IDK-15) gives every data object its own row for the owner, the trial dates, the reconciliation result and the readiness status, so the checks in this article have a place to be tracked.

 [See the Data Migration Plan template (IDK-15)](https://www.ifs-erp.com/en/marketplace/implementation-docs-kit/15-data-migration-plan-and-readiness-checklist) [Read: Data Migration Governance Checklist](https://www.ifs-erp.com/en/blog/the-data-migration-governance-checklist)
