---
title: "Procurement Clause Phrases in IFS Cloud: Setup Guide"
date: 2026-01-01
description: "Procurement clause phrases in IFS Cloud: clause types, dated revisions, connection rules and Generate, so suppliers get one approved text on each PO."
author: "Dariusz Mysliwiec"
intro_image: "https://www.ifs-erp.com/images/articles/procurement-clause-phrases-in-ifs-cloud-en-df0dc3f4.webp"
fulltext_image: "https://www.ifs-erp.com/images/articles/procurement-clause-phrases-in-ifs-cloud-en-df0dc3f4.webp"
categories:
  - name: "Blog"
    url: "https://www.ifs-erp.com/blog.md"
tags:
  - name: "Procurement Clauses"
    url: "https://www.ifs-erp.com/tags/procurement-clauses.md"
  - name: "Phrase Texts"
    url: "https://www.ifs-erp.com/tags/phrase-texts.md"
  - name: "Purchasing"
    url: "https://www.ifs-erp.com/tags/purchasing.md"
  - name: "Procurement Clause Phrases"
    url: "https://www.ifs-erp.com/tags/procurement-clause-phrases.md"
  - name: "IFS Cloud"
    url: "https://www.ifs-erp.com/tags/ifs-cloud.md"
---

# Procurement Clause Phrases in IFS Cloud: Setup Guide

![Procurement Clause Phrases in IFS Cloud: Setup Guide](https://www.ifs-erp.com/images/articles/procurement-clause-phrases-in-ifs-cloud-en-df0dc3f4.webp)

IFS Cloud | Purchasing · Procurement clauses

 
## Procurement clause phrases put one approved supplier instruction, with dated revisions and translations, on IFS Cloud purchase orders

 A procurement clause phrase in IFS Cloud is a reusable text with revisions that prints on the purchase order and tells the supplier which rules to follow. It replaces the instructions buyers type by hand into order notes, and it only works when clause types and connection rules are configured deliberately and Generate is part of the buyer's routine.

 **Key takeaways**

 
- IFS Cloud picks the clause revision by date: the promised delivery date on a purchase order line and the wanted receipt date on a purchase requisition line.
- Connection rules match on seven source line parameters: Site, Part, Supplier, Commodity Group 2, Project, Sub Project and Activity. An empty parameter matches any value.
- Clauses do not appear on lines by themselves. Someone runs Generate on the requisition or order, or connects a phrase manually where the clause type allows it.
- Obsoleting a revision is irreversible and does not touch lines already connected to it, so those lines need a manual decision.

 Free-text notes on a purchase order fail in a predictable way. Two buyers word the same packaging requirement differently, a German supplier receives a Polish note, and an instruction copied from an order two years old still quotes a limit that has since changed. A procurement clause library in IFS Cloud solves this with one approved text per requirement, a revision per period and a translation per language. Clauses describe what the supplier is told. Whether the order then moves as planned is a separate question, covered in [Purchase Order Exception States You Cannot Ignore](https://www.ifs-erp.com/en/blog/order-states-that-need-attention-ifs-cloud).

  ## 1.What a procurement clause is made of in IFS Cloud

 A procurement clause in IFS Cloud has four layers: the clause type, the phrase, the phrase revision with its text, and the connection to a requisition or order line. Each layer has its own owner, and when one person edits all four, buyers can no longer tell an approved text from a draft.

 
### Clause type

 The procurement clause type controls how its phrases are rolled out and how much freedom the buyer has. The Manual Connection Allowed option decides whether a buyer may add a phrase of that type by hand, and Manual Disconnection Allowed decides whether a buyer may remove one. If phrases of a type require approval before they become active, an approval template has to exist. In practice I set up separate types for logistics and quality requirements, for hazardous goods and for legal terms.

 
### Phrase and revision

 The phrase is the requirement, and the revision is its wording for a period. A requirement that changes over time, such as a mercury content limit of 8% for 2025 and 5% for 2026, is held as one phrase with two revisions. A revision is edited while it is Inactive or Approval Required, then activated, and finally made Obsolete. Obsolete is the last status and cannot be reversed.

 
### Phrase text and languages

 Phrase text can be written in every language installed in IFS Cloud, and the language code of the text decides the language in which it is displayed and printed. The text field uses a multi-line editor, and the formatting applied there carries over to printed purchasing documents.

  ## 2.How IFS Cloud picks the right clause revision

 IFS Cloud fetches the valid phrase revision from a date on the source line: the promised delivery date for a purchase order line and the wanted receipt date for a purchase requisition line. The order date and the print date do not decide which wording the supplier receives.

 A purchase order placed in December for delivery in February therefore gets the revision valid in February, which is usually what the requirement intends. After a large change to the promised delivery date, check which revision is connected to the line, because the date that selected it is no longer the date on the order.

 The Define Procurement Clause Phrase Text activity on [docs.ifs.com (IFS Cloud 25R2)](https://docs.ifs.com/ifsclouddocs/25r2/Procurement/ActivityDefineProcurementClausePhraseText.htm) describes revisions and languages, and the Connect Procurement Clause activity in the same documentation describes the date rule.

  ## 3.Connection rules decide which lines get which clause

 A procurement clause connection rule links a phrase to source line parameters, and the Generate command uses these rules to connect phrases to lines. The parameters are Site, Part, Supplier, Commodity Group 2, Project, Sub Project and Activity.

 All parameters in one rule line are combined with AND, and an empty parameter counts as any value. A rule with Supplier filled and every other field empty therefore applies to every line for that supplier. A rule with Site and Commodity Group 2 filled applies only to lines that match both. A hazardous goods clause is a good fit for Commodity Group 2, while a project-specific quality requirement belongs on Project or Sub Project.

 
| Requirement | Rule parameters | Setting to consider |
| --- | --- | --- |
| Packaging standard for one supplier | Supplier only | Manual disconnection not allowed |
| Safety data for chemicals | Commodity Group 2, optionally Site | Approval required before a revision becomes active |
| Certificate for one critical part | Part | Show in Receipt |
| Customer requirement on a project | Project or Sub Project | Manual connection allowed for additions |

 Rules replace the buyer's memory with a lookup, which matters most when purchasing knowledge sits with one or two people. The risk of that concentration is described in [Buyer Knowledge Risk in IFS Cloud Procurement](https://www.ifs-erp.com/en/blog/buyer-knowledge-concentration-risk-ifs).

  ## 4.Generate, manual connection and what prints

 Procurement clauses reach a requisition or order line through the Generate command or through Create/Edit Procurement Clauses, and neither runs on its own in standard IFS Cloud. Rules configured without Generate in the buyer's routine are why a clause library can exist while no clause ever prints.

 
1. **Generate.** Connects the predefined phrases that match the connection rules. On a purchase requisition line the status must be Planned, Released, Authorized or Partially Authorized. On a purchase order line the order must be Planned or Released.
2. **Create/Edit Procurement Clauses.** Opens the phrase connections assistant on a purchase order in status Planned. The buyer either picks a predefined phrase, which brings the active revision for the line date, or writes a one-off text without a predefined phrase.
3. **Active Connection.** A manually created line prints on documents only when Active Connection is enabled on it. A connection can be deleted only until Active Connection is enabled.
4. **Show in Receipt.** When enabled, the phrase is visible to the person receiving the purchase order line, which is where a certificate or inspection instruction is useful.

 The status rules explain a support question that comes with this setup. A buyer who releases an order and then tries to add a clause manually finds that manual creation is limited to Planned orders, while Generate still works on Released ones.

  ## 5.Procurement clauses or document text?

 Document text and procurement clauses are two ways to print text on IFS Cloud purchasing documents. Document text prints through an output type, and procurement clauses connect to requisition and order lines.

 My rule in projects is simple. General terms of purchase that apply to every order belong in document text. A requirement that changes over time, depends on the part, supplier or project, needs a translation per supplier language, or has to be visible at receipt belongs in a procurement clause, because a clause has dated revisions and connection rules, and its connection can be shown at receipt.

  ## 6.Implementation pitfalls I check first

 - **Old notes copied one to one.** A library built from historical order notes repeats their inconsistencies. Group the notes by requirement, rewrite each one once and have it approved before it becomes a phrase.
- **No owner for the library.** When every buyer can create phrases, the same requirement soon exists in several versions. One person or team approves new phrases and revisions, which the approval template on the clause type can enforce.
- **Obsolete revisions left on open lines.** Obsoleting a revision does not change lines connected before, so open orders keep the old wording until someone handles them.
- **Missing translations.** A phrase with no text in the supplier's language cannot print in that language. Test the purchase order printout for one supplier per language before go-live.
- **Generate outside the routine.** If the order process does not include Generate, the rules exist and the supplier sees nothing.

 Clauses are also a clean-core choice: they are standard configuration and need no modification to tell suppliers what is required, which keeps them out of the retesting load at each release. The wider argument is in [Clean Core in IFS Cloud: Purchasing & Inventory](https://www.ifs-erp.com/en/blog/clean-core-ifs-cloud-scm). A clause tells the supplier what to do. It does not tell you whether the supplier confirmed the order, and unconfirmed purchase orders in status Released are one of the three exceptions the [SCM Exception Scan](https://www.ifs-erp.com/en/applications/scm-exception-scan) reports.

  ## 7.Frequently asked questions

 Are procurement clauses added to purchase order lines automatically in IFS Cloud? Procurement clauses are not added to purchase order or requisition lines automatically in standard IFS Cloud. A user runs the Generate command, which connects phrases that match the procurement clause connection rules, or connects phrases manually through Create/Edit Procurement Clauses when the clause type allows manual connection.

   Which clause revision does IFS Cloud print on a purchase order? IFS Cloud connects the procurement clause phrase revision that is valid on the promised delivery date of the purchase order line. For a purchase requisition line the date used is the wanted receipt date. The revision must be in status Active to be connected.

   How do I put one procurement clause on every order for a supplier in IFS Cloud? Create a procurement clause connection rule in IFS Cloud with only the Supplier parameter filled. Empty parameters count as any value, so the rule matches every requisition and order line for that supplier when Generate runs. Disabling Manual Disconnection Allowed on the clause type stops buyers removing it.

   What happens to open purchase orders when a clause revision is made obsolete? Making a procurement clause phrase revision obsolete in IFS Cloud does not change source lines connected before the change. Open purchase order lines keep the connection to the old revision until someone handles them manually. Obsolete is the final status and cannot be reversed.

   Can goods receiving staff see procurement clauses in IFS Cloud? Goods receiving staff see a procurement clause in IFS Cloud when Show in Receipt is enabled on the phrase connection. From the receipt pages, only active connections with Show in Receipt enabled are listed, which suits certificate and inspection instructions.

 For how purchase orders are approved before release, see [Purchase Order Approval Workflow](https://www.ifs-erp.com/en/blog/purchase-order-approval-workflow), and for recent changes in the purchasing module, [New Purchasing Functionality in IFS Cloud 25R2](https://www.ifs-erp.com/en/blog/new-purchasing-functionality-in-ifs-cloud-25r2).

  ## 8.About the author

 **Dariusz Myśliwiec:** 18 years hands-on with IFS (Apps 7.5 to 10 and IFS Cloud). IFS Certified Associate Consultant. PRINCE2® 7. Independent practice based in Kraków, delivered remotely across Europe and globally. You talk to the consultant who does the work, not a sales layer.

 In purchasing projects I build the clause types and connection rules with the people who own the requirements, and I test the printed purchase order in each supplier language before go-live.

 **Selected clients from my IFS work:** Fugro · LGC · BVI Medical · Betafence (PRÆSIDIAD) · Barlinek · NGK Ceramics · Newag · Oleofarm.

 IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.

  ## Clauses tell suppliers what to do. Check which orders they never confirmed

 The SCM Exception Scan reads your IFS Cloud data and reports three exceptions: unconfirmed purchase orders in status Released, overdue deliveries with no receipt, and stock below minimum. You get the result in five working days, and nothing is installed in IFS.

 [See the SCM Exception Scan](https://www.ifs-erp.com/en/applications/scm-exception-scan) [Read: Purchase Order Approval Workflow](https://www.ifs-erp.com/en/blog/purchase-order-approval-workflow)
