Go-Live
Go-live is the point where an IFS Cloud solution stops being a project and starts being the way the business works. It is a short moment that rests on months of preparation, and the outcome is usually decided long before the date arrives. This tag gathers material on readiness, cutover and the first weeks of live operation.
What go-live really tests
On the day, every assumption made during design meets real volumes, real users and real deadlines. Data that looked fine in a test load turns out to be incomplete, a role that nobody tried is missing a permission, and an interface that worked with ten messages struggles with a thousand. A calm go-live is the result of finding those problems earlier, not of luck on the weekend.
The building blocks
- Readiness decision: agreed criteria and a named group that says go or no-go, with the evidence in front of them.
- Cutover plan: a timed sequence of tasks with owners, dependencies and checkpoints, including what is frozen in the old system and when.
- Contingency: a rollback or fallback path that has been thought through, with the point after which it is no longer possible.
- Hypercare: a defined period of extra support after go-live, with a clear way to log, rank and close issues.
Practical experience
Rehearse the cutover at least once with realistic data and time it, because the plan on paper is always shorter than the plan in practice. Keep the decision criteria written down so that the discussion on the final evening is about facts and not about pressure. Make sure business users, not only the project team, have signed off the processes they will depend on on Monday morning.
Articles under this tag include templates for the cutover plan and the readiness decision, and describe how to prepare the organisation as well as the system. They are meant to be adapted to your own project, not copied unchanged.