Template IDK-12, version 1.0. Phase: Establish Solution.

How to use this template

  • Use one specification per configuration or report in the CRIM log (template IDK-10): custom fields, custom events, page configurations, lobbies, workflows, quick reports and operational reports. Integrations and modifications use template IDK-11.
  • Fill sections 1 to 3 for every object. In section 4, keep only the block that matches the object type and delete the others.
  • Build starts only after the customer project manager has approved in section 9. Changes after approval go through change control.
  • Keep it short. A good configuration specification fits on a few pages and can be read by the process owner.
  • Replace every [...] field. Delete the rows marked Example: before approval.
Template metadata
Field Value
Template ID IDK-12
Phase Establish Solution
Owner Application consultant or customer technical analyst
Approver Customer project manager
Qualification gate Solution Established
Version 1.0

Document control

Field Value
Project [Project name]
CRIM log ID [ID]
Object type [Custom field / Custom event / Page configuration / Lobby / Workflow / Quick report / Operational report / Other]
Solution area and process [Area, process, link to process model]
Author [Name, role]
Builder [Name, role]
Status [Draft / In review / Approved / Built / Tested / Accepted]
Storage location [Link]
Version Date Author Change Approved by
0.1 [YYYY-MM-DD] [Name] First draft  
[x.y] [YYYY-MM-DD] [Name] [Change] [Name]

1. Business need and standard alternative

Item Description
Business need Example: Goods receivers must see at arrival whether a purchase order line needs a supplier certificate, so that goods without one go to the quarantine location
Requested by [Name, business role]
Book of Rules reference [Document, decision ID]
Standard alternative considered Example: Note text on the purchase order line was shown. It is free text, cannot be searched or made mandatory, and is often left empty.
Why a configuration is justified [Text]
Consequence if not delivered [Text]

2. Object and context

Item Description
Object name [Name following the project naming convention]
Naming convention reference [Link. Agree a prefix so customer objects are easy to find at update time.]
Page, entity or report the object belongs to Example: Purchase order line entity, shown on the purchase order page and on the arrival registration page
Configuration context (page configurations) [Global, or the named context and the rule that maps users or sites to it]
Sites and companies in scope [List]
Business roles that use it [Roles]
Related CRIM objects [IDs]

3. Logic in plain language

Describe what the object does so that the process owner can confirm it. One short paragraph or a numbered list.

Example:

  1. A buyer ticks "Certificate required" on the purchase order line when the part belongs to a regulated part group.
  2. The goods receiver sees the field, read-only, when registering the arrival.
  3. When the field is ticked and no certificate is attached, a notification goes to the quality role.

[Your text]

4. Object detail

Keep the block that applies. Delete the rest.

4.1 Custom field

Item Value
Entity [Entity name as shown in entity configuration]
Field name and label Example: CERT_REQUIRED, label "Certificate required"
Data type and length Example: Boolean
Persistent or read-only (calculated) [Persistent / Read-only, with the expression for read-only fields]
Default value [Value]
Mandatory [Yes / No, and from which status]
Value list or reference [Enumeration values or referenced entity]
Pages where the field is placed [Page, group, position]
Needed in reports, lobbies, integrations or migration [List, with CRIM IDs]
Translations needed [Languages]

4.2 Custom event and event action

Item Value
Entity and table the event listens to [Name]
Fires when [New record / Modified record / Removed record, and on which attributes]
Condition Example: Certificate required is true, and the line status changes to arrived
Action type [E-mail / Streams message / Execute online SQL / REST call / Other]
Recipients or target [Role-based address or distribution, not a named person]
Message content [Subject and body, with the substitution fields used]
Expected frequency [agree in project]
What happens if the action fails [Text. An event action that raises an error can block the user's transaction. State the intended behaviour.]

4.3 Page configuration

Item Value
Page [Page name and navigator entry]
Change Example: Add custom field to the line group, hide two unused fields, make the confirmed date column visible by default
Configuration context [Context]
Conditional formatting or mandatory rules [Rule]
Before and after screenshots [Link]
Interaction with user personalisation [Note whether users' own saved layouts are affected]

4.4 Lobby

Item Value
Lobby page name Example: Buyer start page
Audience [Business roles]
Page parameters [For example site, buyer, date range]
Element Type Data source Filter and grouping Drill-down target Refresh expectation
Example: Unconfirmed lines Counter with list Purchase order lines Released lines without confirmation, by buyer, older than [agree in project] days Purchase order lines page with the same filter On page load
[Element] [Type] [Data source] [Filter] [Target] [Expectation]

Performance note: [Expected row counts per data source, and any data source that needs an index or a narrower filter].

4.5 Workflow (Business Process Automation)

Item Value
Workflow name [Name]
Purpose [Validation / Enrichment of data / User interaction / Background process]
Trigger [Projection and action or entity operation that starts it, and timing relative to the standard logic]
Steps [Numbered list or BPMN diagram link]
Data read and written [Projections, entities, fields]
Messages shown to the user [Text and language]
Behaviour on failure [Whether the user's transaction is stopped, and the message shown]
Volume expectation [agree in project]

4.6 Quick report

Item Value
Report name and category [Name, category]
Type [SQL statement / Query designed in the client]
Parameters [Name, type, default, mandatory]
Columns [Column, source, format]
Selection logic in plain language Example: All open purchase order lines where the promised date is earlier than today, for the sites the user is allowed to see
Data sources [Views or projections. State how site and company access is respected.]
Expected row count and run time [agree in project]
Output use [On screen / Export / Scheduled]

4.7 Operational report

Item Value
Standard report used as the base Example: Purchase order print-out
Layout name [Name]
Changes to layout [Logo, address block, columns added or removed, terms text]
Additional fields needed [Field, source. Note whether the report data must be extended, which raises the tailoring level.]
Languages [List]
Paper format and output channel [Format, print, e-mail, archive]
Legal or customer-mandated content [Text and the person who confirmed it]
Layout mock-up [Link]

5. Permission sets affected

Permission set Change Reason Security owner informed
Example: [Buyer role permission set] Grant access to the lobby page and its data sources Buyers open it as start page [Name, date]
Example: [Goods receiver permission set] Read access to the custom field, no edit Field is maintained by buyers only [Name, date]
[Permission set] [Change] [Reason] [Name, date]

Test with an end-user login that holds only the listed permission sets. An object that works for an administrator proves nothing.

6. Test cases

Test ID Class Login role Preconditions and data Steps Expected result Result, tester, date
Example: T1 Common Goods receiver Purchase order line with "Certificate required" ticked Open arrival registration for the line Field is visible and read-only [Pass / Fail], [Name], [YYYY-MM-DD]
Example: T2 Normal exception Buyer at another site Same line Open the purchase order Order is not accessible, in line with site access  
[ID] [Common / Normal exception / Specific exception] [Role] [Data] [Steps] [Expected]  

Included in SAT script: [ID].

7. Update-safety note

Item Description
Tailoring level Configuration, unless section 4.7 requires extended report data
Standard objects this configuration depends on [Pages, entities, fields, views, report]
What must be re-verified at each release update Example: Field still placed correctly on both pages, event still fires, test cases T1 and T2
What may break and how it would be noticed [Text]
Owner of re-verification after go-live [Customer role]
Retirement condition [When standard covers the need, this object is removed]

8. Deployment

Item Description
Built in environment [Environment]
Moved by [Configuration package, named and versioned / manual steps listed here]
Target environments and order [Test, SAT, production or reference environment]
Post-deployment steps [Publish, approve, synchronise, grant, refresh]
Cutover plan entry needed [Yes / No]
Step-by-step guides to update [Guide IDs]

9. Approval

Build may start once the customer project manager has approved. The process owner confirms that section 3 matches the agreed way of working.

Role Name Decision Date Signature
Customer process owner (logic confirmed) [Name] [Approved / Approved with comments / Rejected] [YYYY-MM-DD]  
Customer project manager [Name]      
Technical solution manager (reviewed) [Name]      

Acceptance after test:

Role Name Test evidence reference Date Signature
Customer process owner [Name] [Link] [YYYY-MM-DD]  

Comments and conditions: [text]