The project manager starts the handover and the project budget pays for it. Plan it as a project task with a date, not as something that happens when people have time.
Prerequisites: the customer is live (a partial handover per site or module is possible), the solution is accepted, and the documentation is in English.
Write for a support consultant who has never met this customer. If that person cannot find a specification or reproduce a test from this document, the handover is not finished.
Rows marked Example: show the expected level of detail. Delete them from your working copy.
Close with a recorded handover meeting between the project team and support (section 12). Without the meeting the handover has not happened.
IFS Cloud release and service update level at handover
[release, update]
Go-live date(s)
[date per site or module]
User base
[Named users by type: link to licence record]
Business-critical periods
[Period end, seasonal peaks, shift patterns]
Support agreement reference
[Contract, service hours, response commitments: link]
Further rollouts planned
[Sites, modules, dates]
2. Project contacts
Role
Name
Organisation
Contact
Available after handover until
Customer sponsor
[name]
[Customer]
[email, phone]
[YYYY-MM-DD]
Customer project manager
[name]
[Customer]
[email, phone]
[YYYY-MM-DD]
Customer system owner after go-live
[name]
[Customer]
[email, phone]
Permanent
Customer IT lead
[name]
[Customer]
[email, phone]
Permanent
Expert users per area
[link to list]
[Customer]
Permanent
Supplier project manager
[name]
[Supplier]
[email, phone]
[YYYY-MM-DD]
Solution architect
[name]
[Supplier]
[email, phone]
[YYYY-MM-DD]
Technical solution manager
[name]
[Supplier]
[email, phone]
[YYYY-MM-DD]
Application consultants per area
[names]
[Supplier]
[email]
[YYYY-MM-DD]
Account manager
[name]
[Supplier]
[email, phone]
Permanent
Who at the customer may log support cases: [names or rule]. Who may approve chargeable work: [names].
3. Handover checklist
#
Item
Done
Evidence / link
Comment
1
Customer is live in the handover scope
[ ]
[Go-live confirmation]
2
Solution accepted by the customer
[ ]
[SAT and ORT sign-off]
3
Documentation is in English
[ ]
4
Process model is current and accessible to support
[ ]
[link]
5
CRIM log complete, with latest functional and test specifications
[ ]
[Section 6]
6
Third-party integrations listed with owners and accounts
[ ]
[Section 7]
7
Extensions and localisations listed
[ ]
[Section 8]
8
Environments documented; support has the access it needs
[ ]
[Section 5]
9
Delivery schedule and readiness reviewed
[ ]
[Section 9]
10
Basic data to adjust after go-live listed with owners
[ ]
[Section 10]
11
Known issues and workarounds listed; open cases transferred
[ ]
[Section 11]
12
Project accounts and elevated access removed or given an end date
[ ]
[Account list]
13
Handover meeting held and recorded
[ ]
[Section 12]
4. Solution overview
Item
Value
Process model
[Link to the project in the IFS Scope Tool or exported model]
End-to-end processes in use
[list]
Operating model summary
[Link to the approved Book of Rules documents]
Key design decisions
[Link to decision log. Include the reasoning, not only the outcome.]
Step-by-step guides
[Library link]
Roles and permission sets
[Link to role matrix]
Lobbies in daily use
[list with owner]
Workflows and event actions in use
[list with purpose and owner]
Plain-language summary of how this customer uses IFS Cloud and what is unusual about it: [short text. This is the paragraph a new support consultant reads first.]
5. Environments
Environment
Place
Purpose
Release and update level
Refreshed from / when
Access for support
Owner
[name]
[Build Place / Use Place]
[purpose]
[level]
[source, date]
[Yes / No, how]
[name]
Example: PROD
Example: Use Place
Example: Production
[level]
Not applicable
Example: On request through the customer IT lead, time-limited
Example: Customer IT lead
Example: [name]
Example: Build Place
Example: Development and delivery of modifications
[level]
[YYYY-MM-DD]
Example: Supplier technical team
Example: Technical solution manager
Delivery route from Build Place to Use Place production: [steps, approver, who applies deliveries]. Code repository and branch rules: [link, text]. Identity provider and single sign-on setup: [summary, owner].
6. CRIM objects handed over
Every configuration, report, integration and modification delivered by the project. A fix cannot be verified without a test specification, so a missing link in this table is an open handover item.
CRIM ID
Type
Name and purpose
Process
Functional specification (link, version)
Test specification (link, version)
Version in production
Built by
Re-verify at each update
[ID]
[C / R / I / M]
[text]
[process]
[link, x.y]
[link, x.y]
[x.y]
[name]
[Yes / No]
Example: CRIM-017
Example: Configuration
Example: Custom field "Internal project code" on purchase order line, shown on the supplier order report
Example: Procure to pay
[link, x.y]
[link, x.y]
[x.y]
[name]
Yes
Example: CRIM-003
Example: Integration
Example: Outbound payment file to the bank in the agreed format
Example: Procure to pay, supplier payment
[link, x.y]
[link, x.y]
[x.y]
[name]
Yes
Confirmation: specifications above are the latest versions and match what runs in production. Confirmed by [technical solution manager] on [YYYY-MM-DD].
7. Third-party integrations
Include everything that reads from or writes to IFS Cloud, also services the project did not build.
#
System / service
Purpose
Direction
Projections / interface used
Account and permission set
Authentication
Customer owner
Vendor contact
Check after each update
How to remove
[n]
[name]
[purpose]
[Inbound / Outbound / Read-only]
[list]
[account, permission set]
[method]
[name]
[contact]
[what to verify]
[steps]
Example: 1
Example: External monitoring service for purchasing exceptions, supplied by a third party, running inside the customer network
Example: Alerts purchasers to orders the supplier has not confirmed and to late deliveries
Example: Read-only. Reads through OData. Writes nothing to IFS Cloud and installs nothing in it.
Example: Purchase order and supplier projections: [projection names]
Example: Dedicated service account [account name] with one read-only permission set [permission set name]. No end-user permission sets granted.
Example: [IAM client / method as configured]
Example: Procurement manager (business), customer IT lead (account)
[contact]
Example: Projections still exist and return the fields in use; service account still active
Example: Revoke the permission set, deactivate the account, stop the service. Nothing to uninstall in IFS Cloud.
Example: 2
Example: Bank
Example: Payment files out, statements in
Example: Outbound and inbound
Example: See CRIM CRIM-003, CRIM-004
[account, permission set]
[method]
Example: Finance lead
[contact]
Example: File format unchanged; test file accepted
[steps]
Legacy interfaces stopped at go-live: [link to the closed part of the interface register].
8. Extensions and localisations
Item
Type
Supplier / source
Version
Purpose
Licence or contract reference
Update dependency
[name]
[Extension / Localisation / Partner product]
[name]
[x.y]
[text]
[ref]
[Must be updated with each release update: Yes / No]
Example: Country localisation for [country]
Example: Localisation
[source]
[x.y]
Example: Statutory reporting and tax handling for the legal entity in [country]
[ref]
[Yes / No]
9. Delivery schedule and readiness
Delivery
Content
Planned
Status
Readiness for support
Owner
[Go-live scope per site or module, later rollouts, outstanding CRIM deliveries]
[text]
[YYYY-MM-DD]
[Live / Planned / In build]
[Handed over / Stays with project until: date]
[name]
Example: Site [site], distribution and procurement
Example: All in-scope processes
[YYYY-MM-DD]
Live
Handed over
Supplier PM
Work that stays with the project team after this handover: [list with end dates]. Rule for routing cases during the overlap: [text].
10. Basic data to adjust after go-live
Settings deliberately set for cutover or the first period of use, which someone must change later. If nobody owns them, they stay wrong.
#
Basic data / setting
Current value and why
Target value
When
Owner
Done
[n]
[setting]
[text]
[text]
[date or trigger]
[name]
[ ]
Example: 1
Example: Authorisation limits for purchase orders
Example: Set high for the first period so that approvals do not stop purchasing while approvers learn the process
Example: Limits from the approved procurement policy
[YYYY-MM-DD]
Example: Procurement manager
[ ]
Example: 2
Example: Users with temporary extra permission sets granted for go-live support
Example: Expert users hold wider access during the support period
Example: Role-based permission sets only
[YYYY-MM-DD]
Example: Security lead
[ ]
11. Known issues and workarounds
ID
Description
Area
Workaround in use
Case reference
Owner
Planned fix
[ID]
[text]
[area]
[text]
[ref]
[name]
[Delivery, service update or date]
Example: R-006
Example: Supplier order report shows the custom project code only on the first page
Example: Procurement
Example: Purchasers add the code to the order note for multi-page orders
[ref]
[name]
[delivery]
Open support cases with the software vendor at handover: [list or link]. Residual issues from the closure document: [link to template IDK-24, section 4].
12. Handover meeting record
Field
Value
Date
[YYYY-MM-DD]
Attendees, project team
[names]
Attendees, support
[names]
Attendees, customer
[names]
Recording
[link]
Agenda
[Customer and solution overview; CRIM walkthrough; integrations; environments and delivery route; known issues; basic data to adjust; questions from support]
#
Question or action from the meeting
Owner
Due
Closed
[n]
[text]
[name]
[YYYY-MM-DD]
[ ]
Support start date: [YYYY-MM-DD]. From this date cases go to: [channel].
Approval
Role
Name
Decision
Date
Signature
Supplier project manager (owner)
[name]
[Submitted]
[YYYY-MM-DD]
Technical solution manager
[name]
[Confirms sections 5 to 8]
[YYYY-MM-DD]
Support manager
[name]
[Accepted / Accepted with open items / Rejected]
[YYYY-MM-DD]
Customer project manager
[name]
[Accepted / Rejected]
[YYYY-MM-DD]
Customer system owner
[name]
[Accepted / Rejected]
[YYYY-MM-DD]
Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.
Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.
Login Form
ROI Calculator
Calculate your return on investment
Input Values
€
€
€
Results
Annual Savings
€ 0
Payback Period
0 months
ROI
0%
Monthly Savings
€ 0
We Value Your Privacy
We use cookies to enhance your experience and for traffic analysis. By continuing to visit this site you agree to our use of cookies.