Template IDK-20, version 1.0. Phase: Implement Solution (prepared and rehearsed), Go Live (executed).

How to use this template

  • This is one document with two levels of detail. Section 2 plans the period around go-live by day. Section 3 plans the days around go-live by hour.
  • Draft both before the first rehearsal. Durations in sections 3 and 5 must come from a rehearsal with full data volumes, never from an estimate. Rehearse more than once.
  • During the cutover this is a live document. The cutover manager updates actual times as tasks finish and reviews status in short, frequent meetings.
  • Rows marked Example: show the expected level of detail. Delete them from your working copy.
  • The contingency plan (section 9) is approved together with the plan. A cutover without a written way back is not ready for the gate.
Template metadata
Field Value
Template ID IDK-20
Phase Implement Solution (prepared and rehearsed), Go Live (executed)
Owner Cutover manager
Approver Steering group
Qualification gate Go Live Authorised
Version 1.0

Document control

Field Value
Project [Project name]
Customer [Legal entity]
Go-live scope [Companies, sites, processes]
Planned go-live date [YYYY-MM-DD]
Document owner [Name, cutover manager]
Status [Draft / Rehearsed / Approved / In execution / Closed]
Version [x.y]
Storage location [Link. Also keep an offline copy during the cutover.]
Related documents [Data migration plan, go-live readiness decision (template IDK-21), communication plan, legacy decommissioning strategy, handover to support (template IDK-22)]
Version Date Author Change
[0.1] [YYYY-MM-DD] [name] [First draft]

1. Cutover organisation

Role Name Contact during cutover Backup
Cutover manager [name] [phone] [name]
Customer project manager [name] [phone] [name]
Supplier project manager [name] [phone] [name]
Data migration lead [name] [phone] [name]
Technical lead, environments [name] [phone] [name]
Integration lead [name] [phone] [name]
Business validation leads per area [names] [phone] [names]
Decision maker for go / rollback [name, role] [phone] [name]

Status reviews during cutover: [times, channel, attendees]. Decision rule when the decision maker cannot be reached: [text].

2. Cutover plan (day granularity)

Workstreams: data migration, configuration switches, communications, legacy decommissioning, support arrangements, infrastructure, business preparation.

ID Day Workstream Task Owner Depends on Planned Actual Status
[ID] [YYYY-MM-DD] [workstream] [task] [name] [ID] [YYYY-MM-DD] [YYYY-MM-DD] [Not started / In progress / Done / Late]
Example: C-012 [YYYY-MM-DD] Example: Business preparation Example: Stop creating new purchase orders in legacy; urgent buys recorded on the agreed manual form for entry after go-live Example: Procurement manager Example: C-008 supplier notice sent [YYYY-MM-DD]   Not started
Example: C-015 [YYYY-MM-DD] Example: Data migration Example: Final extract of supplier, customer and part master data from legacy; control totals recorded Example: Data migration lead Example: C-012, C-013 [YYYY-MM-DD]   Not started

Business freeze periods:

Process Freeze starts Freeze ends Manual procedure during freeze Owner
[Process] [date, time] [date, time] [text or link] [name]

3. Cutover checklist (hour granularity)

Seq Planned start Planned end Task Owner Predecessor Checkpoint Actual start Actual end Status
[n] [day, hh:mm] [day, hh:mm] [task] [name] [Seq] [None / Go-no-go / Point of no return]      
Example: 14 [day, hh:mm] [day, hh:mm] Example: Set legacy to read-only for order entry, purchasing and inventory transactions Example: Legacy system administrator Example: 13 None      
Example: 15 [day, hh:mm] [day, hh:mm] Example: Run Data Migration Manager jobs for open purchase orders; compare loaded line count and value with extract control totals Example: Data migration lead, procurement validation lead Example: 14 Go-no-go      

Rules for the checklist:

  • Every task has one named owner who is present or reachable at the planned time.
  • Every planned duration is the longest duration seen in rehearsal, plus the buffer agreed in the project: [agree in project].
  • A task is done when its owner reports it to the cutover manager. Not before.

4. Time-critical configuration switches

Settings that must stay off until a precise moment, or be changed at a precise moment.

# Switch Environment From To When (checklist seq) Owner Verified by
[n] [setting] [Production] [state] [state] [Seq] [name] [name]
Example: 1 Example: Scheduled background jobs for order processing and planning Production Example: Inactive Example: Active with production schedule [Seq] Example: Technical lead Example: Supply chain lead
Example: 2 Example: Integration routing to external parties (supplier order output, bank files) Production Example: Test endpoints or disabled Example: Production endpoints [Seq] Example: Integration lead Example: Finance lead
[n] [Workflows and event actions that send email to suppliers or customers]            
[n] [Number series start values]            
[n] [Accounting periods opened for user groups]            
[n] [End users activated and attached to production permission sets]            

5. Data migration run order

Data Migration Manager loads through standard business logic. Invalid records are rejected at load, so the order matters and every load needs a reject check.

Order Data set Method Source Depends on Duration in rehearsal Planned duration Validation Validated by
[n] [data set] [Data Migration Manager / Copy and paste / Manual entry] [system, file] [Order no.] [from rehearsal log] [from rehearsal log plus buffer] [Control totals, record count, spot check] [name]
Example: 3 Example: Suppliers with addresses, payment terms and purchase part links Example: Data Migration Manager Example: Legacy extract file [name] Example: 1 basic data, 2 parts [from rehearsal log] [from rehearsal log plus buffer] Example: Record count equals extract; reject list empty or each reject explained; spot check by purchasers Example: Procurement lead
Example: 7 Example: Inventory on hand per location Example: Data Migration Manager Example: Legacy stock count extract after final count Example: 2 parts, 5 locations [from rehearsal log] [from rehearsal log plus buffer] Example: Quantity and value per site equal legacy stock report Example: Inventory lead, finance lead

Reject handling: [who reviews rejects, who corrects source data, how a reload is approved].

6. Communications

Audience Message Sender Channel When Feedback route Done
Project team [Cutover schedule, roles, status meeting times, contact list] [Cutover manager] [channel] [YYYY-MM-DD] [channel] [ ]
Users [Freeze dates, first login instructions, where to get help, where the guides are] [Customer PM] [channel] [YYYY-MM-DD] [Expert users] [ ]
Business and management [Go-live decision, expected disruption, status updates during cutover, confirmation of go-live] [Sponsor] [channel] [YYYY-MM-DD] [Steering group] [ ]
Suppliers [New document layouts, changed order numbers, ordering pause, contact for questions] [Procurement manager] [channel] [YYYY-MM-DD] [mailbox] [ ]
Customers [Delivery and invoicing pause, changed document layouts, contact for questions] [Sales manager] [channel] [YYYY-MM-DD] [mailbox] [ ]
Example: Suppliers Example: No purchase orders will be issued between [YYYY-MM-DD] and [YYYY-MM-DD]. Orders after that carry a new number format. Confirmations go to [address]. Example: Procurement manager Example: Email to supplier contacts from the migrated supplier master [YYYY-MM-DD] Example: Procurement mailbox [ ]

7. Legacy decommissioning

System / interface Action at go-live Action later Data retention need Owner Date
[system] [Read-only / Stopped / Runs in parallel for: reason] [Archive / Switch off / Contract end] [Legal or audit requirement] [name] [YYYY-MM-DD]
Example: Legacy ERP Example: Read-only for all users at checklist seq [n] Example: Archive and switch off after the period in the decommissioning strategy Example: Financial records per local law Example: IT manager [YYYY-MM-DD]

Legacy interfaces to stop: [list from the interface register with owner and checklist seq].

8. Support arrangements

Item Arrangement
First-line contact Expert users per site and area: [link to list]
Second line [Core team, location, hours]
Supplier go-live support [Who, on site or remote, period: agree in project]
Issue logging [Tool, who may log, triage time]
Floor walking [Schedule per site]
Service desk [Trained in basic administration: Yes / No. Scope: password, user activation, printer routing.]
Status meetings after go-live [Frequency and length: agree in project]
Transition to regular support [Date, see handover to support (template IDK-22)]

9. Contingency plan

9.1 Triggers

Trigger Measured how Decision
[Condition that makes continuing unsafe] [evidence] [Pause / Rollback / Continue with workaround]
Example: Inventory balances do not reconcile with legacy after reload Example: Value per site against legacy stock report Example: Pause at go-no-go checkpoint; rollback if not resolved before the point of no return

9.2 Point of no return

Item Value
Definition [The checklist step after which legacy can no longer be reinstated without losing or re-entering business transactions]
Checklist seq [Seq]
Planned time [day, hh:mm]
Decision maker [name, role]
Inputs to the decision [Data validation sign-offs, switch verification, open issues]
After this point Problems are fixed forward in IFS Cloud. Section 9.3 no longer applies.

9.3 Rollback steps

Step Action Owner Planned duration Verified by
1 [Announce rollback decision to team and management] [Cutover manager] [from rehearsal]  
2 [Deactivate end users and background jobs in IFS Cloud production] [Technical lead] [from rehearsal]  
3 [Stop production integration routing; restore legacy interfaces] [Integration lead] [from rehearsal]  
4 [Remove read-only state from legacy; confirm legacy data is as at freeze] [Legacy administrator] [from rehearsal]  
5 [Enter transactions recorded manually during the freeze into legacy] [Business leads] [from rehearsal]  
6 [Inform users, business, suppliers and customers] [Customer PM, sponsor]    
7 [Schedule review and new go-live decision] [Steering group]    

Rollback has been rehearsed: [Yes / No, date, result].

10. Rehearsal log

Rehearsal Date Environment Data volume Completed
[n] [YYYY-MM-DD] [name] [Full / Partial: reason] [Yes / No]
Rehearsal Task (seq) Planned duration Actual duration Why it took longer or failed Change made to the plan Owner
[n] [Seq] [value] [value] [reason] [change] [name]
Example: [n] Example: 15, open purchase orders load [value] [value] Example: Rejects caused by suppliers missing purchase part links; reload needed Example: Add pre-load check query on part links to seq 12; move supplier validation earlier Example: Data migration lead

Decision after rehearsal: [Plan accepted / Another rehearsal required on: date]. Decided by: [name].

11. Backup before release to users

Item Value
What is backed up [Production database and file storage after final data validation, before user activation]
Requested from [Cloud service provider / Customer IT: procedure reference]
Checklist seq [Seq, directly before user activation]
Confirmed by [name]
Confirmation reference [ticket or log entry]
Restore responsibility and procedure [name, link]

Users are not released until the backup is confirmed.

Approval

Role Name Decision Date Signature
Cutover manager (owner) [name] [Submitted] [YYYY-MM-DD]  
Customer project manager [name] [Approved / Rejected] [YYYY-MM-DD]  
Supplier project manager [name] [Approved / Rejected] [YYYY-MM-DD]  
Customer IT lead [name] [Approved / Rejected] [YYYY-MM-DD]  
Steering group chair [name] [Approved / Rejected] [YYYY-MM-DD]  

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

ROI Calculator

Calculate your return on investment

Input Values

€
€
€

Results

Annual Savings
€ 0
Payback Period
0 months
ROI
0%
Monthly Savings
€ 0

Get Detailed Report

Enter your details to receive a detailed ROI report.