Template IDK-21, version 1.0. Phase: Implement Solution.

How to use this template

  • This is the paper the steering group reads before it authorises go-live. Send it in advance, not on the day.
  • Every criterion needs evidence that someone can open and read: a signed report, a log, a list. "We believe so" is not evidence.
  • Area owners fill in their own status. The project managers challenge it. The steering group decides.
  • Rows marked Example: show the expected level of detail. Delete them from your working copy.
  • Three outcomes are possible: go, go with conditions, no-go. A no-go taken on evidence is a sound decision. Record it with the same care as a go.
Template metadata
Field Value
Template ID IDK-21
Phase Implement Solution
Owner Customer project manager
Approver Steering group
Qualification gate Go Live Authorised
Version 1.0

Document control

Field Value
Project [Project name]
Customer [Legal entity]
Go-live scope [Companies, sites, processes]
Proposed go-live date [YYYY-MM-DD]
Decision meeting date [YYYY-MM-DD]
Document owner [Name, customer project manager]
Status [Draft / Submitted / Decided]
Version [x.y]
Storage location [Link]
Related documents [SAT and ORT sign-off (template IDK-18), training record (template IDK-19), cutover plan (template IDK-20), handover to support (template IDK-22)]
Version Date Author Change
[0.1] [YYYY-MM-DD] [name] [First draft]

1. Summary for the steering group

Item Value
Recommendation of the project managers [Go / Go with conditions / No-go]
Areas ready [list]
Areas ready with conditions [list]
Areas not ready [list]
Main remaining risk [One sentence]
Decision needed by [date, because: reason]

Status legend used below: Ready / Ready with conditions / Not ready / Not applicable.

2. Readiness criteria by area

2.1 Solution

# Criterion Evidence Owner Status
S1 SAT completed, documented and approved by the steering group [Link to SAT completion report] [Test lead]  
S2 All CRIM objects delivered to production and tested [CRIM log with status] [Supplier PM]  
S3 No open defect that blocks deployment [Defect log filter] [Test lead]  
S4 Production functional and technical configuration complete and matches the accepted baseline [Configuration checklist] [Solution architect]  
S5 Load test signed off, if required by the test strategy [Report or "Not required" decision] [Customer IT lead]  
Example: S2 Example: Custom fields on purchase order line, supplier order report layout and bank payment file format are in production at the version tested in SAT Example: Handover to Support (template IDK-22), section 6, production version per CRIM object Example: Supplier PM Example: Ready

2.2 Data

# Criterion Evidence Owner Status
D1 Migration routines validated with full volumes [Rehearsal log] [Data migration lead]  
D2 Each data set validated and signed by its data owner in the latest load [Validation sign-offs] [Data owners]  
D3 Cleansing of legacy data complete or remaining work accepted [Cleansing tracker] [Data owners]  
D4 Reconciliation method for balances agreed with finance [Reconciliation procedure] [Finance lead]  
D5 Manual data entry tasks planned with owners and time [Cutover checklist] [Cutover manager]  

2.3 Users and training

# Criterion Evidence Owner Status
U1 ORT completed; expert users signed the confirmation statement [Link to ORT statement] [Test lead]  
U2 End-user training delivered; absentees have a catch-up date before go-live [Attendance record] [Training lead]  
U3 Step-by-step guides final and available to all users [Guide library link] [Training lead]  
U4 Expert users named per site and area, and known to users [Expert user list] [Customer PM]  

2.4 Security

# Criterion Evidence Owner Status
X1 Roles and permission sets built and tested with role-based logins [Role matrix, SAT evidence] [Security lead]  
X2 Users attached to roles in production [User and permission set export] [Security lead]  
X3 Segregation of duties conflicts reviewed and accepted [Review record] [Finance lead, auditor contact]  
X4 Project and consultant accounts reviewed; elevated access has an end date [Account list] [Customer IT lead]  
X5 Integration and service accounts hold only the access they need [Account list with permission sets] [Integration lead]  

2.5 Infrastructure and environments

# Criterion Evidence Owner Status
I1 Production environment at the agreed release and service update level [Environment record] [Customer IT lead]  
I2 Network access, single sign-on and identity provider tested from every site [Test record per site] [Customer IT lead]  
I3 Printers, label printers, scanners and mobile devices tested at each site [Device checklist] [Site leads]  
I4 Backup before release to users arranged and confirmed [Cutover plan section 11] [Customer IT lead]  
I5 Update freeze agreed around go-live [Update strategy (template IDK-23)] [Customer IT lead]  

2.6 Integrations

# Criterion Evidence Owner Status
N1 Every interface in the interface register tested end to end with the external party [Interface register with test status] [Integration lead]  
N2 Production endpoints, certificates and credentials in place and verified [Checklist] [Integration lead]  
N3 Monitoring and error handling for each interface has a named owner [Interface register] [Integration lead]  
N4 Legacy interfaces to be stopped are listed in the cutover checklist [Cutover checklist] [Cutover manager]  
Example: N1 Example: Bank payment file accepted by the bank in its test channel; supplier order output received and confirmed by the pilot suppliers Example: Interface register, column "External confirmation" Example: Integration lead Example: Ready with conditions

2.7 Cutover

# Criterion Evidence Owner Status
C1 Cutover plan and checklist approved [Link] [Cutover manager]  
C2 Full-volume rehearsal completed; durations fit the available window [Rehearsal log] [Cutover manager]  
C3 Contingency plan approved; point of no return and decision maker named [Cutover plan section 9] [Cutover manager]  
C4 Cutover team confirmed available, including backups [Cutover organisation table] [Both PMs]  
C5 Communications to users, business, suppliers and customers scheduled [Cutover plan section 6] [Customer PM]  

2.8 Support

# Criterion Evidence Owner Status
P1 Go-live support resourced on site for the agreed period [Resource plan] [Supplier PM]  
P2 Issue logging and triage process for the go-live period agreed [Cutover plan section 8] [Customer PM]  
P3 Service desk trained in basic administration [Training record] [Customer IT lead]  
P4 Handover to support scheduled [Template IDK-22, planned date] [Supplier PM]  

2.9 Business readiness

# Criterion Evidence Owner Status
B1 Line managers confirm their teams are staffed for go-live and the period after [Confirmations] [Business leads]  
B2 Changed policies and procedures published [Procedure list] [Change lead]  
B3 Organisation changes linked to the new processes in effect [Change plan] [Change lead]  
B4 Manual procedures for the freeze period known to the affected teams [Cutover plan section 2] [Business leads]  
B5 Sponsor and steering group members visible to the business during go-live [Communication plan] [Sponsor]  

3. Open items

# Area Item Impact if not closed Owner Due Needed before go-live
[n] [area] [text] [text] [name] [YYYY-MM-DD] [Yes / No]
Example: 4 Example: Integrations Example: One pilot supplier has not confirmed receipt of the new order format Example: Orders to this supplier sent manually by email until confirmed Example: Procurement manager [YYYY-MM-DD] Example: No, workaround accepted

4. Timing considerations

Consideration Assessment Conclusion
Business peaks [Seasonal peaks, campaigns, large deliveries around the proposed date] [OK / Conflict: text]
Holidays and absences [Public holidays per country, school holidays, planned absence of key people on both sides] [OK / Conflict: text]
Financial period [Period or year end, closing activities, opening balances, audit dates] [OK / Conflict: text]
External parties [Bank, authority or partner deadlines; supplier and customer shutdowns] [OK / Conflict: text]
Update calendar [Planned service or release update near go-live] [OK / Conflict: text]
Competing projects [Other changes landing on the same users] [OK / Conflict: text]
Fallback date [Next possible date if this one is missed, and what it costs] [YYYY-MM-DD]

5. Decision record

Field Value
Meeting date [YYYY-MM-DD]
Present [names, roles]
Papers sent in advance on [YYYY-MM-DD]
Decision [Go / Go with conditions / No-go]
Go-live date confirmed [YYYY-MM-DD]
Reason for the decision [text]

Conditions (for "go with conditions"):

# Condition Owner Must be met by Verified by If not met
[n] [text] [name] [date, time] [name] [Go-live is postponed / Escalate to: name]

For a no-go:

Field Value
Criteria not met [IDs from section 2]
Actions to reach readiness [text, owners]
Next decision date [YYYY-MM-DD]
Communication of the postponement [Who informs whom, by when]

Approval

Role Name Decision Date Signature
Customer project manager (owner) [name] [Submitted] [YYYY-MM-DD]  
Supplier project manager [name] [Recommends go / go with conditions / no-go] [YYYY-MM-DD]  
Project sponsor [name] [Go / Go with conditions / No-go] [YYYY-MM-DD]  
Steering group chair [name] [Go / Go with conditions / No-go] [YYYY-MM-DD]  

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.