Independent IFS Cloud practice · Implementation
Test environments you can trust: how many IFS Cloud needs and how to refresh them
An IFS Cloud project needs one environment for each purpose that has to stay stable while it is in use: configuration, integration testing, acceptance testing and production, plus training and cutover rehearsal on larger projects. The count matters less than three rules: every environment has a named purpose, every refresh is planned around a test cycle, and a copy of production in test is treated as personal data.
Key takeaways
- There is no IFS-prescribed number of environments. Derive the layout from the project phases: what is built where, what is tested where, and what must not change during an acceptance cycle.
- A test result only proves something if you can name the environment, the date it was last refreshed and the source it was refreshed from. The IDK-18 test script has a field for exactly that.
- In the projects I run, a refresh is a planned event with an owner, an export of environment-specific settings before it and a checklist after it, and it is never a favour done on the Friday before acceptance.
- The first things to check after a copy from production are outgoing e-mail and integration endpoints, because a test system with production addresses can contact real suppliers.
- A copy of production contains employee, supplier and customer contact data. Under UK GDPR that data needs a reason to be there and a limit on who can open it.
The project has one test environment, three months in it no longer resembles production, and at acceptance nobody can say which results still count. The other version of the same problem is quieter: a fresh copy of production is loaded for testing and the first purchase order that is released sends a real e-mail to a real supplier. This article sets out how I lay out environments in an IFS Cloud implementation and how a refresh should be run, and then what to do about personal data in test. Where a statement is my own project practice rather than documented IFS behaviour, I say so, because the details of cloning depend on your hosting model and your agreement with IFS.
1.How many environments does an IFS Cloud project need?
An IFS Cloud project needs as many environments as it has purposes that cannot share a system without damaging each other. IFS does not set a norm for this, and I would distrust any answer that gives a single number without asking about the project. A small single-site rollout can run on a configuration environment, one test environment and production. A multi-site rollout with integrations, a data migration and a formal acceptance cycle usually needs more, because the people testing cannot work on a system that the configuration team changes every day.
The table below is the layout I start from in projects, then reduce or extend.
| Environment purpose | What happens there | What it must not do |
|---|---|---|
| Configuration | Build and configure the solution, run early migration loads, prototype | Serve as the place where acceptance is signed |
| Integration test | Connect interfaces to the test systems of third parties and verify messages end to end | Point at a production system of a third party |
| Acceptance (SAT, ORT) | Scripted acceptance on frozen configuration and a known data state | Change configuration during a test cycle without a recorded decision |
| Training | Teach key users and end users on realistic but safe data | Hold unmasked personal data that trainees do not need |
| Cutover rehearsal | Run the cutover plan against a production-like system and time each step | Differ from production in release level or in installed content |
| Production | Live operation | Be used to try something out |
One system can serve two purposes when the schedule allows it, for instance training on the same environment that later becomes the rehearsal system. The rule is that two purposes never run at the same moment on the same system. The Test Strategy template (IDK-17) is where the layout and the rule for each environment get written down, and the Cutover Plan template (IDK-20) is where the rehearsal environment is named.
2.What are Build Place and Use Place?
According to IFS Community users, Build Place is where the IFS Cloud environments of a customer exist, and Use Place is the place where the system runs for its users. I could not find a page in the IFS documentation that defines either term, so this section rests on a community thread and not on documentation: IFS Build Place environments (thread 60929).
According to that thread, Build Place offers environments of three types: Development (DEV), Delivery (DEL) and QA. The number of environments is limited per type, and the limit is shown in Build Place under settings, Environments Quota. Additional environments are ordered from IFS, which means an additional cost and a sales process, so count them in the project budget and the plan before the layout is fixed. Because these are users' answers, confirm the environment types, the quota and the price against your own agreement and the release you run.
On infrastructure that the customer runs, the labels differ and the setup is the customer's own, so the questions in the next sections are answered by your IT team and not by a request to IFS. The principle that non-production systems sit apart from production applies in both models.
3.How does an environment clone or refresh work?
A clone, or refresh, replaces the data and the configuration of a target environment with a copy of a source environment, typically production into test. The mechanics are not something I will describe screen by screen, because I did not find a procedure published by IFS, and the steps depend on the hosting model and the agreement. What I can describe is what each refresh has needed in the projects I run, and what you should ask IFS or your own IT team to confirm in writing before the first one.
- The target is unavailable while it is overwritten. Plan the window and tell the testers, because a refresh that starts at the wrong hour stops a test day.
- Source and target must be at the same release and the same installed content. A copy of production into a test system that already took a newer update will either be refused or give you a system that behaves differently from production.
- Settings that belong to the environment, not to the business, are overwritten too. Integration endpoints, credentials for third-party systems, message routing and system parameters come across from the source. Export or record them in the target before the refresh and reapply them after it.
- Anything built only in the target is lost. A configuration change made in test and never moved to the source disappears with the overwrite, so move or record it first.
- Request the refresh through the channel your agreement defines. For an IFS-managed environment that is a service request with IFS, and the lead time is a question for IFS, not a number I can give you.
Configuration should travel between environments through a controlled transfer and not by retyping it. Which mechanism applies depends on the release and on what kind of change it is, so settle it in the Test Strategy and test it once with a harmless change before you depend on it.
4.When should the test environment be refreshed?
Refresh the test environment before a test cycle starts and not on a calendar, because the date that matters is the one printed on the test result. A refresh just before acceptance gives the testers data that looks like the business. A refresh in the middle of a cycle destroys the evidence collected so far and makes earlier results unrepeatable.
- Before each acceptance cycle: refresh, run the post-clone checklist, freeze configuration, record the date in the test script.
- Before the cutover rehearsal: refresh from the most recent production state the project can use, so that the rehearsal meets realistic volumes and master data.
- Never during a cycle: if a defect needs fresh data, create that data in the environment and note it, or stop the cycle and restart it deliberately.
- After a release update of production: bring the test systems to the same level before the next cycle. The Update Strategy template (IDK-23) covers the update side, and the question of when to test updates is covered in Service Update vs Release Update on the consulting site.
The SAT/ORT Test Script and Sign-off template (IDK-18) carries the field that makes this auditable: the environment used, its last refresh date and the source of the refresh. Without those three values a signed test says only that something passed somewhere.
5.What must be checked after a clone, before users log in?
After a copy from production, a test system still holds production addresses and users, so it can act on the outside world until each of those is switched off or redirected. I run the following checks in order and record the result before anyone is told the system is ready.
| Check | Why it matters after a copy |
|---|---|
| Outgoing e-mail and notifications | Suppliers, customers and employees can receive messages from a test system. Disable sending or route everything to a test mailbox. |
| Integration endpoints and credentials | Interfaces cloned from production point at production systems of third parties. Repoint each to its test endpoint, including e-invoicing, bank interfaces, carriers and EDI partners. The IFS Cloud API integration article covers the integration account side. |
| Background jobs and scheduled tasks | Schedules copied from production start running in test: batch postings, data exports and report distribution. Stop what should not run and re-enable the rest deliberately. |
| Users and permission sets | Production users, including leavers, arrive with their access. Remove or disable who does not belong in test and grant testers what the test roles need. See Designing Audit-Ready Permission Sets in IFS Cloud. |
| Printers and output channels | Print queues and document distribution settings may point at real printers and real recipients. |
| Links and addresses in templates | URLs stored in reports, e-mail templates and external tools can lead back to production. |
| Environment identification | Make it obvious on screen that this is test. A user who mistakes test for production enters real transactions that disappear at the next refresh. |
A read-only monitoring account is a good first thing to create on the non-production system. If you plan to run the SCM Automation Pack, the integration account can be set up on a test environment first, and the first week after installation runs without sending any message, so you see what the system would send before anyone receives it. Nothing is installed in your IFS, so a release update leaves nothing of ours for you to retest; compatibility with the new release is checked on our side under the subscription.
6.Do you have to mask personal data in test environments?
A copy of production in a test environment is still personal data, and UK GDPR applies to it in the same way as to the live system. The articles to read are the data protection principles in Article 5(1), data minimisation in point (c) and storage limitation in point (e), data protection by design in Article 25, and security of processing in Article 32. The regulation does not contain the word "masking". What it asks is that you hold only the personal data you need for the purpose, keep it no longer than needed and protect it appropriately, which for a test copy usually leads to masking or pseudonymisation, or to loading a reduced data set.
In practice I ask three questions about every non-production system:
- What personal data does the copy contain, such as employee records, supplier bank details, contact persons at customers and suppliers, and user names in logs and audit trails?
- Does the test purpose need those values, or only data of the right shape? A purchase-order flow test needs realistic structure and volume, not real bank account numbers or private addresses.
- Who can open the environment, from where, and is that list shorter than the list for production or at least no longer?
ISO/IEC 27001:2022 treats the same topic as a control, which is how it often reaches a project: Annex A 8.31 asks for separation of development, test and production environments and 8.33 asks for test information to be selected, protected and managed. An auditor who reads your Test Strategy will look for both.
Whether your IFS release offers a built-in function to anonymise data in a copy is a question I have not confirmed for this article, so I do not claim one. Ask IFS, and if there is none, agree a masking step in the project, run by the party that owns the data, before testers get access. This is a description of the legal text and of my practice, not legal advice. Your data protection officer or legal adviser decides what is required for your data. The ICO publishes guidance on UK GDPR that your adviser will use.
7.How do I review my environment layout before acceptance testing?
Review the layout by writing one line per environment: purpose, owner, release level, last refresh date, source of that refresh and who has access. A line that cannot be filled in is a finding. Doing this once before the acceptance cycle takes less time than explaining afterwards why a result cannot be reproduced.
If you want a second pair of eyes on the layout and the refresh plan, that is a 30-minute technical call with the person who would do the review. For test practice in general, see IFS Testing on the consulting site.
Book a 30-min technical call See the SAT/ORT test script template
8.Frequently asked questions
How many environments does an IFS Cloud project need?
An IFS Cloud project needs one environment per purpose that cannot share a system with another: configuration, integration testing, acceptance testing and production, and on larger projects training and cutover rehearsal. IFS does not prescribe a number. A small single-site rollout can manage with fewer, a multi-site rollout with integrations and a formal acceptance cycle needs more, and the number included is set by your agreement.
What is the difference between Build Place and Use Place?
According to IFS Community users, Build Place holds environments of three types, Development (DEV), Delivery (DEL) and QA, with a limit per type shown under settings, Environments Quota; extra environments are ordered from IFS at additional cost. Use Place is described by the same users as the place where the system runs for its users. This comes from a community thread (60929), not from IFS documentation, so check your agreement and the release you run before you plan a layout around these names.
Can I refresh the test environment from production, and what survives the clone?
Yes, a test environment is normally refreshed from production, with the target unavailable while it is overwritten and with source and target at the same release. Data and configuration of the target are replaced, which includes environment-specific settings such as integration endpoints, so those must be recorded or exported before the refresh and reapplied after it. Confirm the exact behaviour with IFS or your own IT team for your hosting model.
How often should the IFS Cloud test environment be refreshed?
Refresh the test environment before each acceptance cycle and before the cutover rehearsal, and not during a cycle. The refresh date belongs on the test result, because a result only proves something if the data state it ran on is known. Frequency is therefore tied to the test plan and to production release updates, not to a fixed calendar interval.
Do I have to mask personal data in non-production environments?
UK GDPR does not use the word masking, but a copy of production in test is personal data, and Articles 5(1)(c), 5(1)(e), 25 and 32 require data minimisation, limited storage, data protection by design and appropriate security. For a test copy that usually means masking or pseudonymising data the test does not need and restricting who can open the environment. Your data protection officer or legal adviser decides what applies to your data.
What must be checked after a clone before users log in?
After a clone of production into test, check outgoing e-mail and notifications, integration endpoints and credentials, background jobs and scheduled tasks, users and permission sets, printers and output channels, and links stored in templates. Each of these can still point at production, so a test system can contact real suppliers or customers until it is disabled or repointed. Record the result of the checks before releasing the system to testers.
9.Sources
- UK GDPR (retained Regulation (EU) 2016/679), Articles 5, 25 and 32, legislation.gov.uk
- UK GDPR guidance and resources, Information Commissioner's Office
- ISO/IEC 27001:2022, Annex A controls 8.31 and 8.33 (control numbers only, the text of the standard is not quoted)
- IFS Community thread: IFS Build Place environments (users' answers, not IFS documentation)
The Build Place description comes from the community thread above and is not documentation. Descriptions of clone and refresh behaviour come from project practice, not from a specific IFS documentation page, and they vary with hosting model, release and agreement. Check your agreement and the IFS documentation for the release you run before relying on any of it.
10.About the author
Dariusz Myśliwiec: 18 years hands-on with IFS, today on IFS Cloud. IFS Certified Associate Consultant. PRINCE2® 7. Independent practice based in Kraków, delivered remotely across Europe and globally. You talk to the consultant who builds it, not a sales layer.
Selected clients from my IFS work: Fugro · LGC · BVI Medical · Betafence (PRÆSIDIAD) · Barlinek · NGK Ceramics · Newag · Oleofarm.
IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.
Acceptance testing coming and no clear record of which environment is which?
Bring your environment list and the test plan. On a 30-minute technical call I will go through the layout and the refresh dates with you and tell you what to fix before acceptance starts.