Template IDK-04, version 1.0. Phase: All phases.

How to use this template

  • Set it up during Initiate Project and keep it alive until the closure document is signed. A register that is only opened before a steering group meeting is a report, not a control.
  • The customer project manager owns it. The supplier project manager contributes risks from the delivery side. Every team member may raise an entry.
  • Section 4 is starter content: risks that recur in ERP implementations. Keep the ones that apply, rewrite them for your project, delete the rest. Do not present the starter list as your risk analysis.
  • A risk is something that may happen. An issue has happened. When a risk occurs, close it in the register and open it in the issue log with a reference.
  • It is done for the first gate when the scales are agreed, every open risk has one named owner and a response, and the escalation rule in section 6 is accepted by the steering group.
Template metadata
Field Value
Template ID IDK-04
Phase All phases
Owner Customer project manager (with supplier project manager support)
Approver Steering group
Qualification gate Project Initiated (register and process in place); reviewed at every later gate
Version 1.0

Document control

Version Date Author Change Approved by
0.1 [YYYY-MM-DD] [name, role] Process, scales and starter register  
1.0 [YYYY-MM-DD] [name, role] Baseline for gate Project Initiated [steering group chair]

1. Risk process

Step What happens Who When
1. Identify Risks are collected in workshops, in the weekly project team meeting and from each phase review. Each is written as cause, event, effect: "Because [cause], [event] may happen, leading to [effect]." Anyone; logged by the PMs Continuous
2. Assess Probability and impact are rated with the scales in section 2. The rating comes from section 3. PMs with the person who raised it Within [agree in project] of logging
3. Plan response One response type is chosen: avoid, reduce, transfer, accept. For reduce: concrete actions. For accept: a stated trigger and a fallback. Risk owner Before the next project team meeting
4. Assign and act One named owner per risk. Actions enter the project plan with dates, like any other task. The owner reports progress; the PMs check that actions are actually performed. Risk owner, PMs Reviewed weekly; top risks at every steering group

Closing a risk requires a reason: occurred (moved to issue log), no longer possible, or reduced to a level the steering group accepts.

2. Scales

Ratings are described in words so that two people rate the same risk the same way.

2.1 Probability

Rating Meaning
Low Would surprise the team. No sign of the cause today.
Medium Could reasonably happen. The cause is present but under some control.
High Expected to happen unless something changes. Early signs are already visible.

2.2 Impact

Rating Schedule Cost Solution quality and business operation
Low Absorbed inside the phase; no milestone moves Absorbed inside the workstream budget Inconvenience; a workaround exists and users accept it
Medium A milestone moves but the gate date holds Needs contingency released by the sponsor A process works with a manual step, or a benefit is delayed
High A gate or the go-live date moves Needs a budget decision by the steering group A business-critical process cannot run, or data cannot be trusted

Project-specific definitions agreed for this project: [add or adjust].

3. Rating matrix

Probability \ Impact Low Medium High
High Moderate Major Critical
Medium Minor Moderate Major
Low Minor Minor Moderate
Rating Handling
Critical Reported to the steering group with a response plan. Owner at sponsor or steering group level.
Major In the top-risk list of the status report. Owner at PM or process owner level.
Moderate Managed by the PMs. Reviewed weekly.
Minor Logged and reviewed at each phase end.

4. Risk register

Columns: P = probability, I = impact. Status: open, reducing, accepted, occurred, closed.

4.1 Project-specific risks

ID Raised Risk (cause, event, effect) Area P I Rating Response type Response actions Owner Next review Status
Example: R-101 [YYYY-MM-DD] Because supplier and part data sit in two legacy systems with different numbering, duplicate suppliers may be loaded, leading to split purchase history and wrong payment terms on purchase orders Data, procurement High Medium Major Reduce Procurement data steward merges duplicates in the source before load cycle [n]; match rule agreed; validation query run after every load in Data Migration Manager Procurement data steward [YYYY-MM-DD] Reducing
Example: R-102 [YYYY-MM-DD] Because warehouse roles are defined late, the acceptance test may be run with broad permission sets, leading to access problems discovered only at go-live Security, inventory Medium High Major Reduce Functional roles for warehouse drafted before the security-and-data test cycle; testers log in with end-user permission sets only Technical analyst, security [YYYY-MM-DD] Open
[ID] [YYYY-MM-DD] [risk] [area] [P] [I] [rating] [type] [actions] [name] [YYYY-MM-DD] [status]

4.2 Starter content: risks that recur in implementation projects

Listed roughly from most to least damaging. Rate each for your own project; the P and I columns are left empty on purpose.

ID Risk Typical early sign Response that works P I Suggested owner
S-01 Senior management is not visibly committed Steering group members send deputies; decisions wait Steering group members act as champions in their own areas; attendance and decisions are minuted     Executive sponsor
S-02 The wrong people are on the team, or the right people are not released Workshops attended by whoever is free; core team answers operational calls during sessions Key people with authority to decide; backfill agreed in writing (IDK-03 section 6); extra capacity planned for peaks     Executive sponsor
S-03 Project management is weak Plan not updated; same issues reappear; meetings without actions Realistic plans; plan, do, review cycle per team every week; short whole-team stand-up; risks and issues worked actively     Both PMs
S-04 Scope grows without decision "Small" additions agreed in workshops; consultants building undocumented items Scope baselined in the plan and scope statement and signed by the steering group; every change documented and communicated (IDK-07)     Both PMs
S-05 Pressure for modifications and for keeping legacy interfaces Requests to make the new system look like the old one From the first day, modifications and integrations need steering group authorisation; standard functionality is tried first     Steering group
S-06 Resistance to change Rumours, low workshop engagement, requests driven by habit Communication strategy and plan; messages about benefits for each group; the system is not modified to soothe users     Change lead
S-07 Other projects compete for the same people and attention Core team pulled into other initiatives Sponsor keeps this project among the top business priorities and resolves conflicts at steering group     Executive sponsor
S-08 The solution does not meet the need or the quality expected Tests designed only by the project team; decisions not reviewed Right team; test design involves the wider business; steering group reviews major decisions; unit tests, then end-to-end tests by the team, then by end users     Customer PM
S-09 Data migration fails or arrives late Data sources unknown; cleansing not started; first load attempted late Identify data and sources early; start cleansing early; documented strategy; trained technical team; several full load iterations     Customer data lead
S-10 End users are not trained or do not accept the solution No training plan; trainers not named Plan who is trained, in what, when and by whom; train the trainer; expert users teach their colleagues     Customer PM
S-11 Go-live fails Cutover plan exists only in the supplier's head; no rehearsal Documented and approved cutover plan; rehearsed more than once with full data volumes; rollback plan with a point of no return     Both PMs
S-12 Teething problems after go-live overwhelm the business Help desk unprepared; no local presence Training that shows each user what they personally gain; support present on site; expert users as first contact; help desk trained in basic administration     Customer PM
S-13 Benefits are not realised Business case not looked at after approval Time-bound benefits in the business case; sponsor accountable; reviewed at every steering group     Executive sponsor
S-14 Tailoring blocks future updates CRIM log grows; no one asks how objects behave at the next release update Update cadence discussed at project start; technical solution manager reviews each CRIM item for update impact     Technical solution manager

5. Issue log

An issue is a fact that needs action now. It has a priority, not a probability.

Priority Meaning
High Stops a workstream or threatens a milestone. Needs a resolution path within [agree in project].
Medium Slows work; a workaround exists.
Low Does not affect the plan. Fixed when convenient.
ID Raised Raised by Issue description Area Priority Impact if unresolved Owner Agreed action Due Status Resolution and date Linked risk or change request
Example: I-014 [YYYY-MM-DD] Functional team lead, procurement Approved authorisation rules for purchase requisitions differ between the two companies; the Book of Rules assumes one rule set Procurement High Prototype scenario for requisition approval cannot be finalised Head of procurement Decide on one rule set or document both; decision paper to PMs [YYYY-MM-DD] Open   [CR reference if raised]
Example: I-015 [YYYY-MM-DD] Technical analyst, integrations Third-party transport system has no test instance available for integration testing Integrations Medium Integration INT-03 tested late, risk to acceptance test entry Customer IT lead Request test instance from vendor; interim test with recorded messages [YYYY-MM-DD] In progress   R-[n]
[ID] [YYYY-MM-DD] [name] [issue] [area] [priority] [impact] [name] [action] [YYYY-MM-DD] [status] [resolution] [reference]

Defects found in testing are not logged here. They live in the test tracker with their own classification (cause, blocks deployment, contractual, owner, closure date). Only a defect that threatens a milestone is lifted into this log.

6. Escalation rule

Situation Escalated to By How fast
Risk rated Critical, or any risk whose response needs budget, scope or date change Steering group Both PMs, through the sponsor Next steering group; extraordinary meeting if the decision cannot wait
High-priority issue not resolved by its due date Executive sponsor Customer PM [agree in project]
Issue where the two PMs disagree Both sponsors Either PM, after telling the other [agree in project]
Issue blocked by a person or department outside the project Executive sponsor Customer PM [agree in project]
Any issue whose resolution changes a baseline Change control (IDK-07) Issue owner Before work continues

An escalation is written: the issue, the options considered, the recommendation, the decision needed and the date it is needed by. Putting it in writing often settles it before the meeting.

7. Review rhythm

Review Participants Scope
Weekly project team meeting PMs, workstream leads New entries, overdue actions, Major and Critical risks, High issues
Steering group Steering group Top risks and issues, escalations, trend since last meeting
Phase review PMs, sponsors Full register; lessons feeding the next phase

Approval

Name Role Date Signature
[name] Executive sponsor (customer) [YYYY-MM-DD] ______________________
[name] Customer project manager [YYYY-MM-DD] ______________________
[name] Supplier project manager [YYYY-MM-DD] ______________________

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

ROI Calculator

Calculate your return on investment

Input Values

€
€
€

Results

Annual Savings
€ 0
Payback Period
0 months
ROI
0%
Monthly Savings
€ 0

Get Detailed Report

Enter your details to receive a detailed ROI report.