Template IDK-05, version 1.0. Phase: Initiate Project.

How to use this template

  • Write it during Initiate Project, after the project organisation (IDK-03) is known. Do the stakeholder analysis first (sections 1 to 4), then the plan (sections 5 to 7). The analysis tells you whom the plan is for.
  • The customer project manager owns it, with the change lead if one is named. The supplier project manager adds the project-internal meetings and reports.
  • Replace every [bracketed field]. Delete rows marked Example: once you have your own.
  • Section 3 contains opinions about named people. Keep a restricted version with sections 2 to 4 and circulate the rest.
  • It is done when every stakeholder group in the grid appears as an audience in the plan, every communication has a named sender, and each line says how feedback comes back.
  • Review it at every gate. Audiences change: early on it is managers and the core team, before go-live it is every user and some external parties.
Template metadata
Field Value
Template ID IDK-05
Phase Initiate Project
Owner Customer project manager (with supplier project manager support)
Approver Executive sponsor
Qualification gate Project Initiated
Version 1.0

Document control

Version Date Author Change Approved by
0.1 [YYYY-MM-DD] [name, role] First draft  
1.0 [YYYY-MM-DD] [name, role] Baseline for gate Project Initiated [executive sponsor]

1. Stakeholder analysis: method

Three steps, repeated at each gate:

  1. Identify. List every person or group that is affected by the project, can influence it, or has an interest in its success or failure. Include external parties.
  2. Prioritise. Place each on the power and interest grid in section 3. The position decides the strategy.
  3. Understand. For the key stakeholders, answer the questions in section 4. Ask them directly where possible; a conversation is also the first act of engagement.

2. Stakeholder list

ID Stakeholder (person or group) Organisation, department How the project affects them Power Interest Current attitude Relationship owner
Example: SH-01 Head of procurement Purchasing Owns the future purchasing process and the benefit tied to it; loses local purchasing habits at two sites High High Supporter Executive sponsor
Example: SH-02 Warehouse shift leaders Logistics, [site] Move from paper picking lists to handheld scanning; their teams are the largest user group Low High Neutral, worried about pace at peak times Functional team lead, inventory
Example: SH-03 Finance director Finance Needs period close unaffected by go-live; approves segregation of duties in permission sets High Low at present Neutral Customer PM
Example: SH-04 Key suppliers receiving purchase orders External New order layout and order numbers; changed confirmation routine Low Low Unaware Head of procurement
[ID] [stakeholder] [department] [effect] [High/Low] [High/Low] [champion / supporter / neutral / critic / blocker] [name]

Power means ability to stop, slow or change the project. Interest means how much the outcome matters to them. Rate what is true today, not what you wish.

3. Power and interest grid

Place stakeholder IDs in the cells.

  Low interest High interest
High power Keep satisfied. Give enough to keep them comfortable; do not flood them. Short, factual updates. Consult before decisions that touch their area. IDs: [SH-..] Engage closely. Involve in decisions, meet in person, make every effort to keep them on board. Steering group members belong here. IDs: [SH-..]
Low power Monitor. Watch for changes in position. Minimal effort: general news only. IDs: [SH-..] Keep informed. Regular information and a way to ask questions. They often spot practical problems first and can become advocates. IDs: [SH-..]

Movement to watch: [for example: finance director moves to high interest before period close and go-live; suppliers move to high interest in the weeks before cutover].

4. Understanding key stakeholders

Complete for each stakeholder in "engage closely" and "keep satisfied". One block per person.

Stakeholder: [name, role]. Interviewed by: [name]. Date: [YYYY-MM-DD].

Question Answer
What financial or emotional interest do they have in the outcome? Is it positive or negative? [answer]
What motivates them most in their job? [answer]
What information do they want from the project, and in what form do they prefer it? [answer]
What is their current opinion of the project? Is it based on good information? [answer]
Who influences their opinions in general, and who influences their opinion of this project? Are those people stakeholders too? [answer]
If they are not positive, what would win their support? [answer]
If they cannot be won, how will their opposition be managed? [answer]
Whom do they influence in turn? [answer]

Resulting actions:

Action Owner Due
Example: Walk the finance director through the go-live date options against the period calendar before the steering group paper is sent Customer PM [YYYY-MM-DD]
[action] [name] [YYYY-MM-DD]

5. Communication objectives

Objective How we will know it works
Everyone affected knows why the project exists and what changes for them [for example: short pulse questions after site briefings]
Decisions are understood where they land, including the reason Reasoning recorded with each decision and included in the message
Rumours are answered fast Questions channel answered within [agree in project]
[objective] [measure]

Principles: talk about benefits for the audience, not features of the system. Say what is not yet decided. One message, one sender. Line managers deliver news that changes someone's job; the project supports them with material.

6. Communication plan: the seven questions

Each line answers: who receives, who sends, why, when and how often, what content, how it is delivered, how feedback is gathered.

# Who receives Who sends Why When, how often What content How delivered How feedback is gathered
Example: C-01 Steering group Both PMs Decisions and gate approval [agree in project], papers sent in advance Status report, key design decision papers, change requests (IDK-06) Meeting with pack Decisions and actions in minutes
Example: C-02 All employees at in-scope sites Executive sponsor Explain purpose, timeline, what changes and what does not At project start and after each gate Short message in business language; link to project page Site meeting and intranet Questions mailbox; questions and answers published
Example: C-03 Warehouse operators and shift leaders Warehouse manager, with expert users Prepare for handheld scanning and the new receipt routine From acceptance test onward, [frequency agreed in project] What changes in the daily routine, training dates, who the expert user on each shift is Shift briefing, demonstration on the device Expert users collect concerns and bring them to the functional team
Example: C-04 Key suppliers Head of procurement Avoid rejected orders and late confirmations after go-live Before cutover, date from cutover plan New order layout, order numbering, contact for questions, cutover freeze dates Letter or email from the buyer responsible Buyer follows up by phone with the largest suppliers
Example: C-05 Help desk and support partner Customer PM Readiness for first-line support Before go-live and at handover Support model, expert user list, basic administration tasks, known residual issues Briefing and handover document Open questions logged and answered before go-live
[ID] [audience] [sender] [purpose] [timing] [content] [channel] [feedback route]

7. Meeting calendar

Meeting Purpose Chair Participants Frequency Input Output
Project team meeting Coordinate workstreams, review plan, risks and issues Customer PM PMs, functional leads, solution architect, technical leads Weekly Workstream status, plan, risk register, issue log Action list, updated plan
PM-to-PM meeting Align on plan, resources, upcoming customer tasks, commercial matters Alternating Both PMs Weekly Tracker, budget status Agreed positions, escalations
Project review Ongoing control by the PMs; establishes milestone status Supplier PM Both PMs, workstream leads as needed [agree in project] Master implementation plan, tracker Milestone status for the status report
Steering group Progress, escalations, key design decisions, change authorisation, gate approval Executive sponsor Steering group members (IDK-03) [agree in project], plus each gate Steering group pack (IDK-06), sent in advance Minutes with owned actions, decisions, gate decision record
Phase review Look back at the phase: what worked, what to change; after go-live, the project evaluation Both PMs Core team, sponsors End of each phase; final review after go-live Tracker, risk and issue history, test results Lessons learned, input to next phase plan or closure document
Defect triage Classify and assign defects during test cycles Test lead Test lead, functional leads, application consultants [daily during test cycles, agree in project] Test tracker Classified defects with owner and date
Cutover status review Control of the go-live event [cutover manager] Cutover team Short and frequent during cutover, [agree in project] Cutover checklist Updated checklist, go or stop decisions
[meeting] [purpose] [role] [participants] [frequency] [input] [output]

Meeting rules: agenda in the invitation; decisions and actions recorded with owner and date; records stored in [location] within [agree in project].

8. Channels and ownership

Channel Used for Owner Not used for
Example: Project page on intranet Timeline, news, questions and answers, training calendar Change lead Decisions that affect individuals
Example: Project collaboration space Working documents, action lists Both PMs Communication to the wider business
[channel] [use] [name] [limits]

Project identity: [project name, short description used in all messages, visual identity if any].

9. Communication log

Date Communication (ID from section 6) Sent by Audience reached Feedback received Follow-up
[YYYY-MM-DD] [ID] [name] [audience] [summary] [action, owner]

Approval

Name Role Date Signature
[name] Executive sponsor (customer) [YYYY-MM-DD] ______________________
[name] Customer project manager [YYYY-MM-DD] ______________________
[name] Change lead [YYYY-MM-DD] ______________________
[name] Supplier project manager [YYYY-MM-DD] ______________________

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

Independent template aligned with the IFS implementation methodology. Not an official IFS document. IFS is a registered trademark of IFS AB.

ROI Calculator

Calculate your return on investment

Input Values

€
€
€

Results

Annual Savings
€ 0
Payback Period
0 months
ROI
0%
Monthly Savings
€ 0

Get Detailed Report

Enter your details to receive a detailed ROI report.