Part A (terms of reference) is written once, during Initiate Project, and approved at the first steering group meeting.
Parts B to E are reused for every meeting: standing agenda, status report, key design decision paper (one per decision), minutes.
The two project managers prepare the pack together and send it [agree in project] before the meeting. A steering group that reads papers at the table decides badly or not at all.
Replace every [bracketed field]. Delete rows marked Example: once you have your own.
A pack is done when each decision requested is stated as a question the steering group can answer with yes, no, or a choice between named options.
Template metadata
Field
Value
Template ID
IDK-06
Phase
All phases
Owner
Customer project manager and supplier project manager (joint)
Approver
Steering group chair (executive sponsor)
Qualification gate
Project Initiated (terms of reference approved); used at every gate for the status report and gate decision
Version
1.0
Document control
Version
Date
Author
Change
Approved by
0.1
[YYYY-MM-DD]
[name, role]
Terms of reference drafted
1.0
[YYYY-MM-DD]
[name, role]
Terms of reference approved
[steering group chair]
[meeting no.]
[YYYY-MM-DD]
[names]
Pack for steering group meeting [no.]
A1. Purpose
The steering group is accountable for the money spent and for the work as a whole. It connects the project to the business and is the only body that can change scope, plan or budget.
A2. Responsibilities
Monitor the project against its objectives and benefits.
Approve the project strategies (testing, training, communication, data, infrastructure, business change, legacy decommissioning).
Decide key design decisions brought by the project managers.
Authorise or reject changes to scope, plan and budget, including every modification and integration.
Set priority against competing initiatives and resolve resource conflicts.
Approve each qualification gate and release the next phase.
Act as visible champions of the project in their own business areas.
The steering group does not manage the project day to day. That is the project managers' job.
A3. Members
Name
Role in the company
Role in the steering group
Deputy allowed
[name]
[title]
Chair, executive sponsor
No
[name]
[title, supplier]
Supplier sponsor
[yes/no]
[name]
[head of business area]
Member, represents [area]
[yes/no]
[name]
Customer project manager
Reports, no vote
No
[name]
Supplier project manager
Reports, no vote
No
Members are senior representatives of the business areas most affected. Membership is a commitment of time: [agree in project] per meeting, plus reading the pack.
A4. Working rules
Rule
Agreement
Meeting frequency
[agree in project], plus one meeting per gate. All dates booked at project start.
Quorum
[agree in project]. The chair must be present for a gate decision.
Pack distribution
Sent [agree in project] before the meeting
Decision method
[consensus, chair decides if none]
Decisions between meetings
[written procedure, for example by email with chair confirmation, recorded in the next minutes]
Minutes
Issued within [agree in project], with owned and dated actions
Extraordinary meeting
Called by the chair on request of either PM when a decision cannot wait
Change management check, reported by the change lead: change plan with owners [yes/no], organisation design adjusted to new capabilities [yes/no/in progress], policies and procedures being updated [yes/no/in progress], user advocacy activities running [yes/no].
One paper per decision. Keep it short enough to be read before the meeting; detail goes in an appendix.
Paper ID: KDD-[nn] Title: [decision in one line] Author: [name, role] Date: [YYYY-MM-DD] Decision needed by: [YYYY-MM-DD]